The owner's demands:
Virtual capacity expansion, cost reduction and efficiency improvement, peak-valley arbitrage.
Industrial and commercial energy storage solutions:
Invested by NOVOAGE, the property owner enjoys a share of the profits;
Install two integrated cabinets, with single machine power of 105KW and 215KWh;
The total installed power is 210KW, with a total capacity of 0.43MWh, and it occupies an area of approximately 5 square meters.
Project effectiveness and benefit manifestation:
The project operates with a monthly electricity charging of 12,000 kWh and a monthly electricity discharging of 11,400 kWh. The monthly profit from peak-valley arbitrage is 10,600 yuan;
If the owner does not invest, the monthly income will be 3,170 yuan, and the annual income will be approximately 38,000 yuan.